Services provided:

Cost

$700K

Location

Villawood, NSW

Client

Probuild

One of Beasy’s most interesting demolition projects ever since the company was established. We were engaged by the client to conduct a demolition decommissioning of a redundant section at the Colgate Palmolive factory.

Works included the erection of a 1500 Favco tower crane. Demolition of high level structures including all external bag houses, chimney flues, silos, ducting, walkways and the like back to base structure.

Unforeseen hazardous materials were also removed during the demolition process whilst maintaining our original program.

The factory remained operational during the entire duration of the works. The gallery above shows our limitless capabilities and strengths in structural demolition.